Wetland Walkway Updates

2/14/21: Construction completed on Wetland Walkway!
(From the Daily Construction Report by Brian Bamberger) - A 4 man crew was onsite today. - They worked on: • Removing snow from around, and on, the lumber...
Read more...
2/13/21: Trex is Complete!
(From the Daily Construction Report by Brian Bamberger) - A 4 man crew was onsite today.- They worked on: • Removed snow from around, and on, the lumber to...
Read more...
2/12/21: Rail Around the Trail
(From the Daily Construction Report by Brian Bamberger) - A 4 man crew was onsite today.- They worked on: • Removing snow from around, and on, the lumber to...
Read more...
2/11/21: All the Trex that's fit to lay
(From the Daily Construction Report by Brian Bamberger)
Read more...
2/9/21: I'm Too Trex-y
(From the Daily Construction Report by Brian Bamberger)- A 4 man crew was onsite today.- They worked on: • Removed snow from around, and on, the lumber to...
Read more...
2/7/21: Walkway framing continues
(From the Daily Construction Report by Brian Bamberger)
Read more...
2/6/21: Walkway starts getting framed
(From the Daily Construction Report by Brian Bamberger)- A 4 man crew was onsite today.- They worked on: • Removed snow from around, and on, the lumber to...
Read more...
1/31/21: Prepping the trail to begin building
(From the Daily Construction Report by Brian Bamberger)- A 3 man crew was onsite today.- They worked on:• Cut down the remaining posts to final grade and drop yokes in place.
Read more...