2/13/21: Trex is Complete!

Wetland Walkway Placeholder Logo online version

(From the Daily Construction Report by Brian Bamberger) 
- A 4 man crew was onsite today.
- They worked on:
       • Removed snow from around, and on, the lumber to facilitate access to the lumber
       • Transfer lumber to walkway path to prepare for framing the ramp
       • Fabricate headers upland of wetland walkway area
       • Transfer headers to walkway path and install into post yokes
       • Complete framing the access ramp with support joists and install blocking
       • Complete installation of the Trex
       • Complete installation of posts
       • Begin Installation of railing

ww 2 13 1
Framing progress on access ramp

ww 2 13 4
Installing Trex on the ramp

ww 2 13 3
Railing installation begins 

ww 2 13 2
Post Installation

ww 2 13 5
Final piece of Trex being installed

IMG 1630
Final screw goes into the Trex