(From the Daily Construction Report by Brian Bamberger)
- A 4 man crew was onsite today.
- They worked on:
• Removed snow from around, and on, the lumber to facilitate access to the lumber
• Transfer lumber to walkway path to prepare for framing the ramp
• Fabricate headers upland of wetland walkway area
• Transfer headers to walkway path and install into post yokes
• Complete framing the access ramp with support joists and install blocking
• Complete installation of the Trex
• Complete installation of posts
• Begin Installation of railing
Framing progress on access ramp
Installing Trex on the ramp
Railing installation begins
Post Installation
Final piece of Trex being installed
Final screw goes into the Trex